
NENANA MUNICIPAL AIRPORT
NENANA, ALASKA
2026 Updates
Nenana Municipal Airport Project Update
We’re excited to announce that airfield lighting and signage construction will soon begin at the Nenana Municipal Airport. This initiative, made possible through grant funding from the Federal Aviation Administration (FAA), will improve visibility and enhance safety for pilots and passengers using our local airport.
Update: Posted August 21st, 2026
Project Contacts:
Primary Contact:
Forrester Cook
Project Manager
(907) 865-1295
Secondary Contact
Tammi Schreier
Aviation Planner
(602) 732-7276
Airport Representative
Dan Smith
Airport Manager
(907) 888-9065
To report an emergency or unsafe conditions, please call Anthony De Los Santos at (907) 888-5117 or Dan Smith at (907) 888-9065.
Construction Notes:
• All schedule dates are subject to change due to weather or other unforeseen circumstances.
• To be included on the distribution list for future construction updates, please email info@portofnenana.gov and put "ATTN: Weekly Email Update" in Subject line of your email.
• Check current Nenana NOTAMs to get up-to-date information on closures.
• Use CTAF (122.1) to contact contractor staff on site.
Current Construction Area:
Phase 1C was completed the morning of Friday, August 21st.
Upcoming Construction:
Week of August 23, 2026, to August 29, 2026 – Upcoming Week
Phase 2A – Taxiway A and South side of Apron
Scheduled – Monday August 24, 2026, to approximately Saturday, September 29th
Description of Work to be performed:
-
Replace: Taxiway/apron edge lights, including associated cable and conduit
-
Replace Segmented Circle
-
TWY A closed
-
South side of Apron Closed
-
Segmented Circle unavailable (August 25th though September 3rd)
-
Fuel will remain available
-
Use caution and avoid construction areas enclosed with low level barricades
Week of August 30, 2026, to September 5, 2026 – Second Week Look Ahead
Phase 2B – Taxiway B and North Side of Apron
Scheduled – Saturday August 29th to Wednesday September 2nd
Description of Work to be performed:
-
Replace: Taxiway/apron edge lights, including associated cable and conduit
-
Replace Segmented Circle
-
TWY B Closed
-
North side of Apron Closed
-
Segmented Circle unavailable (August 25th though September 3rd)
-
Fuel/Pilot Lounge will remain available
-
Access to hangars will be maintained
-
Use caution and avoid construction areas enclosed with low level barricades
Future Activity – Schedule Subject to Change
Phase 3 – Runway 4R/22L Closed
Scheduled – September 4 to September 12
August through October 2026
Construction is planned from early August to late October 2026. Work will begin August 3, 2026. The project involves:
-
Replacing edge and threshold lighting and signage for Runway 4L/22R and Runway 4R/22L
-
Replacing edge lighting and signage for Taxiways A, B, and C
-
Replacing visual aids including segmented circle, primary wind cone, and airport beacon
-
Replacing the supplemental wind cone and apron flood lighting
-
Runway designation remarking
-
Constructing an electrical equipment building
-
Obstruction removal
Planned Runway Closures
Runway closures will occur between August 3 and September 24.
Additional Key Information for Runway Users
-
Extended runway closures:
Runway Closure Dates
4L/22R 08-03-26 to 08-22-26
4R/22L 09-04-26 to 09-12-26
4L/22R 09-14-26 to 09-18-26
4R/22L 09-22-26 to 09-24-26
Please refer to current NOTAMs for the most accurate and up-to-date airfield information.
Project Contacts
Please contact the Resident Engineer or the Airport Manager for questions regarding the project.
Resident Engineer: Forrester Cook, DOWL
City of Nenana Contact: Dan Smith, Airport Manager
Please stay tuned and check back for future updates and information as it becomes available.



WELCOME
ENN is a city-owned public-use airport located one mile south of the central business district of Nenana, and roughly 50 air miles southwest of Fairbanks. It is located along the George Parks Highway, a thoroughfare running 323 miles from the Glenn Highway north of Anchorage to Fairbanks.
Nenana Municipal Airport maintains three runways to serve you.
Explore Nenana and discover your next adventure!
PAVEMENT MAINTENANCE COMPLETE

EVENTS

Complete - December 3, 2025
Nenana Airport Lighting and Signage Replacement Project
Public Stakeholder Meeting #2

Complete - June 22, 2022
Nenana Airport ALP Advisory Committee Meeting and Public Open House #1

Complete - September 30, 2025
Nenana Airport Lighting and Signage Replacement Project
Public Stakeholder Meeting

Complete - July 2023
Pavement Maintenance





